Willow Park Neighbourhood Renewal

Willow Park renewal will see the upgrade of stormwater infrastructure on 52 Street/57 Avenue, 53 Street, 54 Street and 55 Avenue that will improve drainage in the area.  

Certain roads and sidewalks in Willow Park will also see a full reconstruction to ensure their continued stability and safety for years to come. In addition, elevated crosswalks will be constructed on 52 Street in front of Willow Park School to improve pedestrian safety.  

Postcard Map Series - 2024 Roads and Backlanes_Page_03.jpg

There may be temporary impacts to street parking, mail delivery, and bussing to complete the work as efficiently as possible. Residents in the area are encouraged to please keep an eye out for signage and additional details from the contractor throughout the season.   

Note: If you have new concrete installed on your property, the application of ice melt can cause damage. The City recommends using sand to control ice on new concrete for the first year. Free sand and chips bins are placed around the City for you – find your closest bin location 

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: Spring - Fall 2024
Funding: City of Leduc
 

Project Update

June 17: A section of 52 Street between 54 Avenue and 56 Avenue will be closed for underground and road work. Willow Park School and Telford Court will only have access from the south. Willow Park Estates, 55 Avenue and 56 Avenue can be accessed from the 57 Avenue entrance.  Pedestrian access will be available throughout the closure on the east sidewalk. 

 54 Street near 57 Avenue closed for storm main and catch basin installation with roadwork to follow.

Phase BCD4 Closure image for website.jpg

 

Date Status
June 27 Underground work is continuing on 54 Street between 57 Avenue and 55 Avenue. Shallow utility conflicts are being resolved on 52 Street from 54 Avenue to 56 Avenue with storm main installation to follow.
June 20 Underground work is wrapping up on the north section of 54 Street at 57 Avenue and is continuing to the south. Roadwork is expected to follow.
52 Street from 54 Avenue to 56 Avenue is closed with removals taking place this week and underground work on the new storm main to follow. Sidewalk on the north side of 57 Avenue is expected to re-open soon once the concrete has cured.
June 14 52 Street between 50 Avenue and 52 Avenue is now open with minor work remaining. Work continues on storm main and catch basin installation on 54 Street near 57 Avenue with roadwork to follow. Starting June 17, a section of 52 Street from 54 Avenue to 56 Avenue. will be closed for underground work and road reconstruction. The new east sidewalk will remain open for pedestrian access.
 
Sidewalk replacement continues on the north side of 57 Avenue and is expected to re-open once all sidewalk is poured and the concrete has cured enough to drive on. Some mailboxes have been temporarily relocated - Canada Post sent out notifications to those affected.
June 6 Phase 1B concrete is finished and paving is anticipated in the next few days (weather permitting). New water main on 56 Avenue is installed and will be tested before being re-opening. Various fire hydrants and catch basins are being replaced throughout the project as underground work continues. Storm main installation is starting on 54 Street and will be followed by roadwork. New sidewalk has been poured on the east side of 52 Street from approx. 54 Avenue to 56 Avenue. New sidewalk on the north side of 57 Avenue. is expected to be poured next week.
May 29 Phase 1A concrete and paving and complete. Phase 1B (52 St. from 51 Ave. to 52 Ave.) is in progress with removals, excavation and base work. Concrete sidewalks and paving will follow. Underground work on the new water main continues on 56 Avenue. Sidewalk replacement continues on the east side of 52 Street and will move to 57 Avenue north side next.
May 22 Phase 1A surface work is nearing completion and the road closure will soon switch to close Phase 1B (and reopen 1A). Concrete sidewalks were poured this week and paving will follow. Underground work continues at 56 Avenue and 52 Street where traffic is able to pass through with only partial lane closures.
May 2 Starting Monday, May 6, 2024, 52 Street will be closed between 50 Avenue and 52 Avenue for road work. Please follow posted signage indicating the road closures and see the detour route below. The road work will be split into two phases, 1A and 1B to allow continuous access to the business parking lot on the west side of 52 Street. Work is anticipated to take four weeks, weather permitting. 
May 1 Preliminary work has started with hydrovaccing to locate existing utilities. Roadwork and underground work are expected to begin in some areas the week of May 6.

Feedback

Have a question about this project? Please fill out our online contact form.