New traffic signal systems will be installed at:  

  • 50th Street and Athapaskan Drive 
    • Jointly funded by the City and adjacent developer 
  • 50th Street and Bella Coola Drive 
    • Includes minor adjustment to the lane configuration 
Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: August 2022
Funding: City of Leduc, Developer
Construction FAQs

Project Updates:

Sept. 29, 2022 Athapaskan is complete and operational, Bella Coola will be active by mid-October
Sept. 8, 2022 Lights have been installed at Athapaskan, and will be commissioned in the next two weeks.  Lights will be installed at Bella Coola Dr. in the next week, with commisioning following Atahapaskan.
Aug. 25, 2022 Line painting for the new lanes is complete.  Electrical work is ongoing, with the lights expected to be raised in the next week.
Aug. 12, 2022 Pole bases have been installed. Line painting at 50 Street and Atahapaskan will be done on Saturday, with the lights expected to be installed the week of August 22.
June 29, 2022 Scheduled - Work will begin on traffic signals at Athapaskan Drive in early August, followed by Bella Coola Drive.
Feb. 17, 2022 Scheduled - Project currently in the design and procurement phase. Additional information will follow prior to construction.