Spine Road and 65 Ave Roadwork

Reconstruction of Spine Road will see the existing gravel roads from Allard Rod to 65 Avenue, and 65 Avenue from 35 Street to Spine Road become paved. 

Roadwork of Spine Road will enhance transportation to the 65 Avenue and QEII Interchange underway. The interchange is expected to be completed in 2025 and will foster trade and improve transportation logistics and access from the Edmonton International Airport and investments to Leduc and throughout the Edmonton Metroplitan Region. 

Postcard Map Series - 2024 Roads and Backlanes_Page_02.jpg

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: Spring - Fall 2024
Funding: City of Leduc
 

Project Update

July 2: Road (Range Road 250) between Allard Avenue and 65 Avenue will be closed for roadwork until fall. Please follow signage for detours.

65th Ave Constuction - Spine Road Closed.jpg

 

June 24-28: 65 Avenue, from 35 Street, to the Spine Road (Range Road 250) intersection will be closed as road reconstruction work begins. Access through the area will be detoured and local traffic only.

Date Status
June 27 Starting the week of July 2, Spine Road (Range Road 250) between Allard Avenue and 65 Avenue will be closed for roadwork until fall.
June 20 65 Avenue will be paved this week (west of the intersection). Closure of the intersection is anticipated to start next week (June 24-28) for reconstruction. Access through the area will be detoured and local traffic only.
June 13 65 Avenue, west of the intersection, is ready for gravel. Work on the intersection will start once the forcemain contractor is finished their crossing work.
June 6 Telus relocation is complete. 65 Avenue fill placement is ongoing.
May 29 65 Avenue fill placement has started. Telus relocates anticipated to be complete by end of next week. 
May 22 Excavation of the gravel road and Telus relocates are ongoing. 
May 9 Use detour to get around 65 Avenue from 35 Street to RR250 as it remains closed for road reconstruction. Telus is expected to start relocates next week.
May 3 65 Avenue from 35 Street to Spine Road (Range Road 250) will be closed from May 6 to June 30 as road reconstruction work begins. Motorists should follow posted detour signage to/from Spine Road using Allard Avenue and 39 Street. 
May 1 Topsoil stripping has started. Telus relocates to start early May.