Lions Park Secondary Trails

A network of gravel trails will be constructed in Lions Park which connects to the paved multiway.  The gravel trails allow residents to enjoy the outdoors, support mountain biking and protect the area by keeping foot traffic in designated areas.  

Postcard Map Series - 2024 Roads and Backlanes_Page_06.jpg

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: Summer - Fall 2024
Funding: City of Leduc

Project Update

Date Status
Oct. 30 Trails are complete and open to the public. The trails will not be maintained throughout the winter. 
Sept. 25  First trail base work complete. Working on trail 2 and 3. Limestone top still needs to be placed once all trails are complete.
Sept. 12 One portion of the trail is nearly complete. Work ongoing for two other sections.
Aug. 22 Trail work is anticipated to start next week. Trail by the cemetery will wait until tree clearing is complete.

Feedback

Have a question about this project? Please fill out our online contact form.