Community Fencing
Community fencing will be constructed in two locations, Doris Smith Park and Grant MacEwan Blvd., to reduce noise.
Contact: | 780-980-7107 / engineering@leduc.ca |
Timeline: | Complete |
Funding: | City of Leduc |
Project Update
Doris Smith Park
A community fence will be built on the west side of the basketball courts.
Date | Status |
Oct. 6, 2023 | Substaintially complete. |
Sept. 14, 2023 | Post installation anticipated to start this week and panelling to follow |
Sept. 1, 2023 | Post installation should start late next week or early the following week. |
Aug. 9, 2023 | Construction to tentatively start in late-August. |
Aug. 2, 2023 | Construction to tentatively start in mid-August. |
Grant MacEwan Blvd.
A community fence will be built along the East side of Grant MacEwan Blvd between Black Gold Drive to the CP railroad.
Date | Status |
Oct. 6, 2023 | All posts are installed and landscaping restorations are ongoing Panel installation is ongoing. |
Sept. 14, 2023 | Fence removal completed. Tree pruning is ongoing. Fence post installation anticipated to start next week. |
Sept. 1, 2023 | Classic Landscapes will be on site mid to late next week to begin removals. |
Aug. 9, 2023 | Pre-inspection scheduled for next week. Tentative start in late-August. |
Aug. 2, 2023 | Construction to tentatively start in mid-August. |
Feedback
Have a question about this project? Please fill out our online contact form.