Seating Nodes (Telford Lake Trail)

Funding Support: Great Trail Capital Improvement Plan Grant
Timeline: 2021 Construction Season (details to come)
Questions about this project? Email:  engineering@leduc.ca
Phone:  780-980-7107

Overview:

Nine seating nodes will be constructed around the new section of the Telford Lake Trail. Bench seating and waste receptacles will be added approximately every 500m along the trail.  

Project Updates

DATE STATUS DETAILS
July 22, 2021 On-time Work is substantially complete.
June 30, 2021 On-time Deficiency work remaining.
June 24, 2021 On-time Furniture is installed. Landscaping work remains. 
June 16, 2021 On-time Landscaping is ongoing. Furniture scheduled to be installed by end of next week. Project anticipated to be complete by end of June. 
June 8, 2021 On-time Pads are poured. Landscaping will begin this week, weather permitting. Anticipated to be complete toward end of June. 
May 31, 2021 On-time Work on the nodes has started. Anticipated 6 to 8 weeks of intermittent construction. 
May 12, 2021 Scheduled Construction anticipated to begin mid-June
May 10, 2021 Scheduled Contract has been tendered and awarded.
April 12, 2021 Scheduled Details to come.