Storage Yard Environmental Assessment

(located at 3719 48 Ave)

Funding Support: Green Municipal Fund
Timeline: 2021
Questions about this project? Email:  engineering@leduc.ca
Phone:  780-980-7107

Overview:

  • A Phase I Environmental Site Assessment (ESA) conducted at the City’s Public Works Storage Yard in Lede Park identified several areas of potential contamination, such as street sweepings, soil piles, and a hydrovac pit.
  • A Phase II ESA then identified the need for a Supplemental Phase II ESA and groundwater monitoring in 2021.
  • Following the Supplemental Phase II ESA, we will determine if a Remedial Action Plan and further work is required by Alberta Environment and Parks.

Project Updates

DATE STATUS DETAILS
Nov. 15, 2021 Complete Stockpile sampling and hydrovac pit sampling and assessment work is complete. Reporting in progress. 
Sept. 3, 2021 On-time Soil sampling and groundwater monitoring is planned for fall 2021.
2021-04-12 On-time The request for proposals has closed, and consultant selection is underway for the Supplemental Phase II and Groundwater Monitoring.