South Telford Sanitary Main Upgrade

Timeline: May - July, 2021
Questions about this project? Email:  engineering@leduc.ca
Phone:  780-980-7107

Overview:

Overview: The Sanitary Main on 44th Street in South Telford is being upgraded from a 200mm line to a 300mm line from 46A Avenue to 47 Avenue. This is in line with the recommendations in the 2018 Sanitary Master Plan to reduce the risk of basement flooding in the area.

Project Updates

DATE STATUS DETAILS
Sept. 22, 2021 On-time Paving is complete. 
Sept. 9, 2021 On-time Contractor is on-site with paving anticipated by the end of the week. 
August 26, 2021 On-time Paving is re-scheduled for September. 
August 13, 2021 On-time Paving scheduled for mid-end next week. 
July 30, 2021 On-time Underground work is complete. Surface work is ongoing. Tentative completion expected for mid-August.
July 22, 2021 On-time Construction started on July 19 at the intersection of 47 Avenue and 44 Street and is progressing south, currently reaching as far as 46 Avenue. Underground work is expected to be complete the week of July 26, with surface repairs to follow.
July 15, 2021 Scheduled Project anticipated to start week of July 19. 
June 30, 2021 Scheduled Tentatively scheduled to start week of July 12
June 8, 2021 Scheduled Construction is scheduled to begin in early July. 
May 31, 2021 Scheduled Construction is anticipated to begin in early July. 
May 10, 2021 Scheduled
Contract has been tendered and awarded. Scheduled to start mid-summer. 
April 12, 2021 Scheduled Project currently in the design and procurment phase and additonal information will follow prior to construction