South Telford Sanitary Main Upgrade
Timeline: | May - July, 2021 |
---|---|
Questions about this project? | Email: engineering@leduc.ca Phone: 780-980-7107 |
Overview:
Overview: The Sanitary Main on 44th Street in South Telford is being upgraded from a 200mm line to a 300mm line from 46A Avenue to 47 Avenue. This is in line with the recommendations in the 2018 Sanitary Master Plan to reduce the risk of basement flooding in the area.
Project Updates
DATE | STATUS | DETAILS |
---|---|---|
Sept. 22, 2021 | On-time | Paving is complete. |
Sept. 9, 2021 | On-time | Contractor is on-site with paving anticipated by the end of the week. |
August 26, 2021 | On-time | Paving is re-scheduled for September. |
August 13, 2021 | On-time | Paving scheduled for mid-end next week. |
July 30, 2021 | On-time | Underground work is complete. Surface work is ongoing. Tentative completion expected for mid-August. |
July 22, 2021 | On-time | Construction started on July 19 at the intersection of 47 Avenue and 44 Street and is progressing south, currently reaching as far as 46 Avenue. Underground work is expected to be complete the week of July 26, with surface repairs to follow. |
July 15, 2021 | Scheduled | Project anticipated to start week of July 19. |
June 30, 2021 | Scheduled | Tentatively scheduled to start week of July 12 |
June 8, 2021 | Scheduled | Construction is scheduled to begin in early July. |
May 31, 2021 | Scheduled | Construction is anticipated to begin in early July. |
May 10, 2021 | Scheduled |
Contract has been tendered and awarded. Scheduled to start mid-summer.
|
April 12, 2021 | Scheduled | Project currently in the design and procurment phase and additonal information will follow prior to construction |