McKay Close Roadwork
Roads and sidewalks on McKay Close will see a full reconstruction to ensure their continued stability and safety for years to come.
During reconstruction, access to your street will be limited and/or unavailable as well as impacts to RV parking, mail delivery and waste collection. We encourage you to make arrangements and move any RVs ahead of construction. We appreciate your patience and cooperation as crews work to complete the construction as quickly and efficiently as possible.
Note: If you have new concrete installed on your property for less than one year, the application of ice melt can cause damage. The City recommends using sand to control ice on new concrete for the first year. Free sand and chips bins are placed around the City for you – find your closest bin location.
Contact: | 780-980-7107 / engineering@leduc.ca |
Timeline: | Complete |
Funding: | City of Leduc |
Project Update
Date | Status |
Aug. 9, 2023 | Paving is complete, landscaping is ongoing. |
July 20, 2023 | Work is ongoing to complete the gravel, with paving scheduled for early the week of July 24. Once paving is complete, the road will reopen and landscaping will be completed. |
July 14, 2023 | Concrete work is done as of this week, with paving crews coming in late next week to begin paving. Landscaping will follow once paving is complete. Road is anticipated to be open by July 25. |
June 22, 2023 | Road construction is ongoing. Subgrade work is expected to be complete by next week and followed by placement of gravel. |
June 8, 2023 | Sidewalks are complete, and the road is now closed. Road construction anticipated to be ongoing until end of June. |
May 25, 2023 | Replacement of separate walk has begun. This should be complete by June 2. On June 5, the road will be completely closed to begin work on the road. |
May 11, 23 | Work is expected to begin next week. Locate flags will be out in advance on site. |