Two access manholes will be installed to the existing box culverts that carry the majority of the downtown cores storm water. This will allow proper access for maintenance and cleaning of the lines. 

Project Updates

DATE STATUS DETAILS
Nov. 17, 2021 Complete Construction is complete. Cleaning and flushing ongoing. 
Sept. 22, 2021 On-time Paving is complete. 
Sept. 9, 2021 On-time Contractor is on-site with paving anticipated by the end of the week.
August 26, 2021 On-time Paving is re-scheduled for early September. 
August 13, 2021 On-time Paving scheduled for mid-end next week. 
July 30, 2021 On-time Underground work is complete. Surface work is ongoing. Tentative completion anticipated for mid-August.
July 22, 2021 On-time Construction started on July 20. Manholes are installed and contractor is working on the backfill and resurfacing. 
July 15, 2021 Scheduled Project anticipated to begin mid-to-late July.
June 30, 2021 Scheduled Construction re-scheduled to August. 
June 8, 2021 Scheduled  Construction is scheduled to begin in early July. 
May 31, 2021 Scheduled Construction is anticipated to begin in early July. 
May 10, 2021 Scheduled
Contract has been tendered and awarded. Scheduled to start mid-summer. 
April 12, 2021 Scheduled Project currently in the design and procurment phase and additonal information will follow prior to construction.