Back Lanes 2023

The following back lanes will undergo reconstruction, to ensure the continued stability and safety of the lane:  

  • Back lane in Corinthia neighbourhood surrounding Mohawk Cres. 
  • Back lanes in Linsford neighbourhood from 45 Ave North to the T-intersection. 
  • Back lanes in Southfork neighbourhood on Songhurst Wynd between Songhurst Way and Southfork Drive. 

Lanes will be excavated down to the base or sub-grade, restabilized, and re-surfaced. Gas lines may be impacted during this work, and the City will work closely with APEX Utilities as needed.  

During reconstruction, access to the back lane will be limited and/or unavailable, and there may be impacts to RV parking and waste collection. Impacted residents are encouraged to make arrangements and move any RVs ahead of construction, and to keep an eye out for specific details and timelines from the contractor as the work begins and progresses.  

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: Spring/Summer 2023
Funding: City of Leduc

Corinthia

Capital Projects 2023 Postcard Map Series_Corinthia Backlanes.jpg

Project Details

Mohawk Cres - Backlanes Staging-LR.jpg

Project Update

Date Status
Nov. 2, 2023 Work is being done to winterize Stages 2 & 3 starting Nov. 2. Cold mix asphalt ramps are being placed where needed for better laneway and driveway access. The laneway accesses will be transitioned with cold mix; any concrete driveways will be ramped; and any driveways that were previously paved will get cold mix asphalt until the spring. Backfilling landscaping will be done where possible. Once the weather permits in the spring, any cold mix placed this fall will be removed and the top lift overlay will be completed along with any remaining landscape restoration. Notices will be delivered in the spring before the final lift is paved. Waste collection has returned to rear laneway collection.
Oct. 26, 2023 With the recent snowfall, crews are working at restoring access to the laneway along with driveways and garages. Depending on weather, paving of the final lift may be deferred into spring 2024.
Oct. 18, 2023 Driveway cutbacks have begun and concrete is being poured.
Oct. 11, 2023 The first lift of asphalt is being paved on October 12, following the first lift of asphalt driveway cutbacks will begin.
Oct. 4, 2023 Work in Stages 2 and 3 continue, and the first lift of asphalt is scheduled for October 12.
Sept. 20, 2023 Top lift of asphalt in Stage 1 is completed and final landscaping is ongoing. Stage 2 and 3 are set to begin on September 21 and will be closed to traffic. Garbage collection for all Stages will remain in the front until the work in all stages is completed.
Sept. 14, 2023 Stage 1 top lift paving is set to occur on Sept. 14, once the top lift is completed Stage 1 will be reopened to residents while landscaping work occurs. Work in Stages 2 & 3 are exppected to begin on Monday, Sept. 18.
Aug. 31, 2023 Starting Sept. 5,  Stage 1 will be closed in order to replace driveways connections and to replace the laneway access near Corinthia Drive. Once the laneway concrete access has sufficiently cured, the final lift of asphalt will be paved. In Stage 3, Apex continues the replacement of the gas line.
Aug. 23, 2023 In Stage 1, the base lift of pavement has been paved and access to the lane is temporarily opened to residents. A second layer of asphalt still needs to be placed along with driveway cutbacks, this will alleviate any gaps between the lane and driveways. After paving has been completed landscaping will be backfilled and finished. In Stage 3, Apex has begun the gasline replacement and is progressing.
Aug. 9, 2023  Final prep on Stage 1 base is occuring which will allow for the first lift of paving to occur around August 18. Apex is finishing up the remaining work on the Stage 2 gas line and should be completed by the end of the week which will allow for Stage 2 to be temporarily reopened for a brief period of time before DeFord begins the reconstruction.
Aug. 2, 2023 The base prep for stage 1 is nearing completion and will be ready for the first lift of asphalt around the middle of August. Apex is finishing up gas tie ins and is expected to be finished stage 2 by the end of next week.
July 26, 2023 Prepping of the lane surface in Stage 1 is underway and progressing. Apex is completing gas line replacement in Stage 2.
July 19, 2023 Apex has completed the gas line replacements in Stage 1 and DeFord will be taking over the site on July 20 and begin prepping the road surface.
July 5, 2023 Apex is completing the final portion of the gas line replacement in the area and should begin to transition the gas service to the new line. DeFord is expected to begin the lane improvements on the week of July 17, weather permitting.
June 21, 2023 Apex is continuing gas line replacements within Stage 1 of the lane.
June 8, 2023 Work is progessing as Apex has begun removal and replacement of the gas line in stage 1 area.
May 31, 2023 Removals are set to begin in stage 1 on June 1 . APEX will take approximatley 3 weeks to replace the gas line in stage 1 on starting June 5.

Linsford

Capital Projects 2023 Postcard Map Series_Linsford Backlanes.jpg

Project Update

Date Status
Sept. 20, 2023 The lane reconstruction in Linsford is complete.
Aug. 31, 2023 Final grading of gravel has begun and concrete driveway cutbacks are expected to occur next week. 
Aug. 23, 2023 Reconstruction of the laneway has begun and the lane is currently closed. Waste and recycle collection will occur in the front street.
Aug. 9, 2023 Apex has completed the gas line replacement in Linsford and DeFord will be starting the lane reconstruction within the next week.
Aug. 2, 2023 Apex is nearing completion on the gas line in Linsford and is expected to finish tie ins by end of day Friday. DeFord is planning to mobilize in on August 9 and begin the reconstruction of the lane.
July 26, 2023 Apex is continuing the gas line replacement in the lane way.
July 19, 2023 Apex has begun work on replacing the gas line in the lane.
July 5, 2023 Apex has sent out notices to the residents in the area affected. Apex is currently scheduled to start the replacement of the gas line on the week of July 17.
June 21, 2023 Tentative start date is week of July 10, approximately a week before construction starts notices will be hand delivered by the contractor indicating an exact date.
   

Southfork

Songhurst.jpg

Project Update

Date Status
Oct. 18, 2023 The lane reconstruction in Songhurst is complete.
Sept. 20, 2023 Concrete driveway tie ins are being finished up in the lane and paving of the second lift will follow.
Sept. 14, 2023 The base lift of pavement has been completed, driveway cutback are being marked out and will be completed within the next couple weeks. Following this the final lift of asphalt will be paved.
Aug. 31, 2023 Gravel has been placed and concrete driveway cutbacks are expected to occur next week.
Aug. 23, 2023 Reconstruction of the laneway has begun and the lane is currently closed. Waste and recycle collection will occur in the front street.
Aug. 15, 2023 Tentative start date of August 21, approximately a week before construction starts notices will be hand delivered by the contractor indicating an exact date.

Feedback

Have a question about this project? Please fill out our online contact form.