Sanitary Line Lining

The Sanitary Lateral Liner program is the installation of liners inside existing sanitary service pipes to extend the life of the pipes. Lining the pipes allows for the rehabilitation of the service lines without major excavation work.  

Approximately 45 residential locations are planned for service line rehabilitation in 2022. Liner will be added up to the property line; however, there is an option for the property owner to complete the remainder of the line to the house (at the property owner’s cost). Notification and pricing details will be provided directly to impacted residents by the contractor.  

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: 2022 - Details TBC
Funding: City of Leduc
Construction FAQs

Project Updates:

Aug. 31, 2022 All of the lateral liners have been completed. Minor inspection work remains.
July 15, 2022 Ongoing - The majority of this work has been completed, only three houses remain.
June 10, 2022 Ongoing - Approximately half of the sewer linings have been completed. The remaining liners are expected to be done within the next 2-3 weeks. 
June 2, 2022 Ongoing - The lining of sewer laterals has begun. Notices were delivered to impacted residents. Installation of a sewer liner is anticipated to take approximately one day per household. The entire lining phase is anticipated to take approximately three weeks.
May 19, 2022 Cleaning of sanitary lines along with the installation of the clean outs at the property line is complete. Supplies for lining are ordered, and the lining of sanitary laterals is scheduled to begin on May 24. 
Apr. 29, 2022 Scheduled - Project has been awarded to contractor. Tentatively scheduled to begin May 4, 2022, starting with the cleaning of sanitary main sewers. 
Feb. 23, 2022 Scheduled - Project currently in the design and procurement phase. Additional information will follow prior to construction.

Feedback

Have a question about this project? Please fill out our online contact form.