Community Fencing

Community fencing will be constructed in two locations, Doris Smith Park and Grant MacEwan Blvd., to reduce noise. 

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: Complete
Funding: City of Leduc

Project Update

Doris Smith Park

A community fence will be built on the west side of the basketball courts. 

Capital Projects 2023 Postcard Map Series_DSP fence.jpg

Date Status
Oct. 6, 2023 Substaintially complete.
Sept. 14, 2023 Post installation anticipated to start this week and panelling to follow
Sept. 1, 2023 Post installation should start late next week or early the following week.
Aug. 9, 2023 Construction to tentatively start in late-August.
Aug. 2, 2023 Construction to tentatively start in mid-August.

 Grant MacEwan Blvd.

A community fence will be built along the East side of Grant MacEwan Blvd between Black Gold Drive to the CP railroad. 

Capital Projects 2023 Postcard Map Series_GMac Fence.jpg

Date Status
Oct. 6, 2023 All posts are installed and landscaping restorations are ongoing Panel installation is ongoing.
Sept. 14, 2023 Fence removal completed. Tree pruning is ongoing. Fence post installation anticipated to start next week.
Sept. 1, 2023 Classic Landscapes will be on site mid to late next week to begin removals.
Aug. 9, 2023 Pre-inspection scheduled for next week. Tentative start in late-August. 
Aug. 2, 2023 Construction to tentatively start in mid-August.

 


Feedback

Have a question about this project? Please fill out our online contact form.