Black Gold Drive Roadwork

Black Gold Drive between 41B Street and Rollyview Road will undergo surface overlays this season to ensure their continued stability and safety for years to come.   

There may be temporary periods of lane closures and detours for motorists. Please follow signage in the area and drive to the posted speed limit. 

Capital Projects 2023 Postcard Map Series_BGD overlay.jpg

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: Complete
Funding: City of Leduc

Project Update

Date Status
Aug. 9, 2023 Work on Black Gold Drive is complete, with a few minor deficiencies still to be addressed.
July 20, 2023 Paving is complete, and line painting is ongoing. Work should be complete by July 26.
June 22, 2023 Paving delayed due to rain, anticipated to resume week of July 3. 
June 8, 2023 Concrete repairs are complete, and and paving is expected the last week of June.
May 25, 2023 Concrete work is ongoing and will be complete by the end of the week. Landscaping will follow early next week, with overlay beginning roughly June 12.
May 11, 2023 Concrete work to begin next week.

Feedback

Have a question about this project? Please fill out our online contact form.