Backlane Reconstruction and Overlay
Funding support: Provincial grant (MSI)
Timeline: Summer - fall 2020
This project includes back lane excavation down to the base (gravel) layer or sub-grade depending upon lane condition. The sub-grade will be re-stabilized and the base and surface will be replaced.
- Birchmount Drive & Birchglen Crescent lane
- Bridgeport Boulevard & Birch Mont Drive lane
- Bridgeport Boulevard lane & Birchglen Crescent
- Bridgeport Boulevard lane (Provisional)
Questions about this project?
Email: engineering@leduc.ca | Phone: 780-980-7107
Project Updates
*Updates provided on a regular basis
Bridgeport Boulevard & Birchglen Crescent (Stage 1)
Date |
Status | Details |
July 30, 2020 | On-time | Backlane paving is complete. Landscaping and driveway adjustment to follow. All waste and recycling pick up at the backlane. |
June 29, 2020 | On-time | First lift of paving is complete. Concrete driveway replacement in progress, the final lift of asphalt paving to begin afterwards. |
June 10, 2020 | On-time |
Construction started this week. Good progress underway. Limited access to the backlane. |
Birchmount Drive & Birchglen Crescent lane (Stage 2)
Date | Status | Details |
July 30, 2020 | On-time | Backlane paving is complete. Landscaping and driveway adjustment to follow. All waste and recycling pickup at the backlane. |
June 29, 2020 | On-time | First lift of paving is complete. Concrete driveway replacement in progress, the final lift of asphalt paving to begin afterwards. |
-- | Scheduled | Will be starting after stage 1 |
Bridgeport Boulevard & Birchmont Drive lane (Stage 3)
Date | Status | Details |
July 30, 2020 | On-time | Backlane paving is complete. Landscaping and driveway adjustment to follow. All waste and recycling pickup at the backlane. |
June 29, 2020 | On-time | Lane excavation underway, access to backlane is limited. |
-- | Scheduled | Will be starting after stage 2 |
Bridgeport Boulevard lane (Stage 4)
Date | Status | Details |
July 30, 2020 | On-time | Backlane paving is complete. Landscaping and driveway adjustment to follow. All waste and recycling pickup at the backlane. |
-- | Scheduled | Will be starting after stage 3 |