Southwick Point and Southwick Way

Southwick Point / Southwick Way shared lane will undergo:

  • A surface overlay on the north half of the lane
  • A reconstruction on the south half of the lane
  • Includes behind the first four dwellings of the lane headed west behind Southwick Way

View Project Sketch

Project Updates

DATE STATUS DETAILS
July 7, 2021 On-time Final gravel touch-ups are completed. Landscaping to follow (timeline to be determined). 
June 30, 2021 On-time Southwick point lane final gravel touch ups and landscaping to be completed once the weather cools. 
June 24, 2021 On-time Southwick point lane is paved. Final touch-ups and landscaping are anticipated to be complete in early July. 
June 16, 2021 On-time The subgrade work and gravel are complete at Southwick Point lane. Asphalt is scheduled for Friday, June 18, weather permitting.
June 10, 2021 On-time Notice provided to immediately impacted residents, with details on construction, garbage collection and parking. 
June 9, 2021 On-time Construction started on June 9 on the Southwick Point lane. Excavation work is anticipated to be complete by the end of the week, with subgrade preparations beginning after. 
June 3, 2021 On-time Work on the Southwick Point lane will start next week (June 7).
May 27, 2021 Scheduled Expected to begin the week of June 7 (weather pending). The contractor will deliver a construction notice directly to impacted residents later next week with further details. 
May 13, 2021 Scheduled The scope of work has been awarded and the contractor is planning the work, which is anticipated to begin in June. More updates to come when contractor is ready to move into the area. 
April 12, 2021 Scheduled Project currently in the design and procurment phase and additonal information will follow prior to construction.