Capital Roads - 42 Street

42nd Street, between Rollyview Road and Caledonia Drive and; Caledonia Drive, between 42nd Street and midway between the Campbell Road loop will undergo:

  • Excavation of the roadway and existing concrete walk down to the subgrade layer.
  • The subgrade will be stabilized, a new gravel base will be placed, new concrete walk will be poured along with private driveway connectors along the length of the project, and a new asphalt surface will be installed. 
  • The road will be closed in segments designed to minimize blocking street access to homes as much as possible.
  • View Project Sketch

Project Updates

DATE STATUS DETAILS
Oct. 7, 2021 On-time Paving is complete and landscaping will be ongoing over the next few weeks. 
Sept. 28, 2021 On-time Paving is complete on 42 Street north of 36 Avenue, and toplift will begin the week of Oct. 4 to complete the project on Caledonia Drive and 42 Street. Topsoil has been placed, and sod will follow the toplift of asphalt. 
Sept. 3, 2021 On-time Concrete is ongoing, and is anticipated to be complete next week with paving to follow. Road is currently open on gravel. 
August 26, 2021 On-time Reconstruction is ongoing between 36 Avenue and Rollyview Road. Concrete is anticipated for next week, with completion toward mid-September, weather pending. 
August 12, 2021 On-time 42 Street from Caledonia Drive to 36 Avenue paving is complete and now open. Closure of the last piece between 36 Avenue and Rollyview Road will begin on Monday and is anticipated to be closed for approximately two weeks. Access to Caledonia Drive and 42 Street will be available via Coady Boulevard. Impacted residents were provided this notice by the contractor. 
July 29, 2021 On-time Concrete is complete on 42 Street from Caledonia Drive to 36 Avenue. Paving is anticipated for late next week. The intersection of Caledonia Drive and 42 Street will be closed for 3 days next week to touch up gravel and pave the intersection. 
July 16, 2021 On-time The intersection of 42 Street and Caledonia Drive is anticipated to be open on gravel by Monday (July 19). Concrete work is beginning on Caledonia Drive next week. 
July 10, 2021 On-time Caledonia Drive has been paved with bottom lift of asphalt and re-opened to traffic. 42 Street is closed between 36 Avenue and Caledonia Drive. The intersection of Caledonia Drive and 42 Street will be closed the week of July 12 for approximately four days (this will be expidited to minimize disruption). 
July 2, 2021 On-time Paving was delayed due to extreme heat. Caledonia Drive is currently being paved, and will be reopened to traffic once paving is complete. Upon reopening of Caledonia Drive (anticipated to occur Monday, July 5), 42 Street will be closed for reconstruction. Impacted residents on 42 Street were provided this notice by the contractor
June 25, 2021 On-time Concrete on Caledonia Drive is complete; paving is anticipated for next week. 
June 18, 2021 On-time Concrete walks on 42 Street are complete and open to pedestrians. The driveway connectors will be filled early next week to allow residents access to their driveways. On Caledonia Drive, the concrete is ongoing and expected to be complete by the middle of next week, followed by the final lift and gravel and asphalt.
June 11, 2021 On-time Stabilizing and gravel have been installed on Caledonia Drive. Concrete walks on Caledonia Drive and 42nd Street are scheduled for next week. 
June 3, 2021 On-time The walks are currently being poured along 42 Street, anticipated to be complete by Monday. Caledonia Drive from 42 Street to the limit at the south has been removed completely, and partially stabilized. Gravel and concrete will begin next week.
May 27, 2021 On-time The walk along 42nd Street will be replaced by June 2, at which point the contractor will be off the road until mid to late June. Caledonia Drive between 42nd Street and Campbell Road is closed for reconstruction; this closure is anticipated to last about 4 weeks. Detours are in place along Campbell Road east and 42nd Street south. 
May 14, 2021 On-time Walks and driveways along the east side of 42 Street have been removed, and are expected to be replaced by next week. Following concrete replacement, the next major phase of work will begin in mid-June. 
May 6, 2021 On-time Underground work has begun, and will be ongoing for the next few days. Sidewalk removal will begin the week of May 10. 
Apr. 29, 2021 On-time Utility repairs began this week, and are anticipated to take approximately two weeks. Sidewalk construction is scheduled to begin on Caledonia Drive the week of May 10. Notices were delivered to the surrounding area, notifying residents of the upcoming construction. 
Apr. 19, 2021 On-time Underground repairs will begin the week of Apr. 26, in anticipation of roadwork scheduled for mid-May. Notices will be delivered to impacted residents the week of Apr. 19. 
Apr. 12, 2021 Scheduled Project currently in the design and procurment phase and additonal information will follow prior to construction.