Capital Roads - 54 Ave

54th Avenue, between 50th Street and 47th Street will undergo:

  • Excavation of the roadway and existing concrete walk down to the subgrade layer.
  • The subgrade will be stabilized, a new gravel base will be placed, new concrete walk will be poured along with commercial entrances, and a new asphalt surface will be installed. 
  • The road will be closed in segments, with access still available by existing lanes.
  • View Project Sketch

Project Updates

DATE STATUS DETAILS
Sept. 28, 2021 On-time Roadwork is complete. Topsoil has been placed and sod will follow next week. 
August 26, 2021 On-time The portion of road from 49 Street west is complete, with only landscaping remaining. Top lift paving will begin east of 49 Street in the next few weeks. 
August 12, 2021 On-time Concrete is ongoing and anticipated to be complete next week. Paving is anticipated to begin toward the end of next week. 
July 29, 2021 On-time Gravel is complete between 50 and 49 Street, concrete will be poured by the end of next week. 
July 16, 2021 On-time Roadwork has begun between 50 Street and 49 Street, and will be ongoing until mid-August. 
July 10, 2021 On-time Work east of 49 Street is mostly complete. Toplift of asphalt will be placed once all the road is reconstructed. The section between 50 Street and 49 Street will be closed the week of July 12 for reconstruction. 
July 2, 2021 On-time Paving was delayed due to extreme heat, and is scheduled for early next week. Removals between 49 and 50 Street will begin once the paving is complete. 
June 25, 2021 On-time Concrete walks between 47 and 49 Streets are complete and the intersection at 49 Street is open. Paving is anticipated for the end of the week. The road between 49 and 50 Street is planned for removal the week of July 5. 
June 18, 2021 On-time Concrete walks are scheduled for the middle of next week. The intersection of 54 Avenue and 49 Street will be open to traffic on Monday on a gravel surface.
June 11, 2021 On-time Stabilizing and gravel are complete. Concrete walks will be poured next week. The intersection of 49th Street and 54th Avenue will be closed for approximately two more weeks. 
June 3, 2021 On-time The road between 49 and 47 Street has been removed, with stabilizing scheduled for Friday and Saturday (June 4 and 5). Gravel will be placed early next week, with concrete planned for the end of next week.
May 27, 2021 On-time Underground work is complete, and the road between 47 & 49 Street will be closed starting May 28 for reconstruction. This closure is anticipated to last three weeks. 
May 14, 2021 On-time Underground work is ongoing, and 54 Ave between 47 & 49 Street will be closed for reconstruction beginning the Tuesday after the May long weekend (May 25). 
May 6, 2021 On-time Underground work has begun, and will be ongoing for the next few days. Sidewalk removal will begin the week of May 10. 
Apr. 29, 2021 Scheduled Utility repairs are scheduled to begin the week of May 3, and are anticipated to take approximately two weeks. Some brief road closures may occur during the underground repairs. Notices were delivered to the surrounding area notifying residents of the upcoming construction. 
Apr. 19, 2021 Scheduled Underground repairs will begin the week of May 3, in anticipation of roadwork scheduled for mid-May. Notices will be delivered to impacted residents the week of Apr. 26.
Apr. 12, 2021 Scheduled Project currently in the design and procurment phase and additonal information will follow prior to construction.