Electric Vehicle Charging Stations


Solar Carport and EV Chargers

A 24.3 kW solar carport has been constructed over six parking stalls in the City-owned parking lot at 4820 – 49 Ave.  A Level 2 and a Level 3 electric vehicle chargers will be installed under the carport.

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: Solar Carport: January - March 2022; EV Chargers: Summer 2022
Funding: Solar Carport - Alberta Municipal Solar Program Grant and City of Leduc; EV Chargers - NRCan's ZEVIP Grant and City of Leduc
Construction FAQs

Project Update:

Sept. 29, 2022 EV Chargers for ATB lot have arrived and will be installed in the next two weeks
June 1, 2022 Scheduled - EV Chargers are on order and will be installed upon arrival. 
May 6, 2022 Scheduled - Solar carport is installed and connected to the grid. EV chargers are in the procurement phase. 
Feb. 17, 2022 Scheduled - Solar Carport installation is underway and it will soon be connected to the electricity grid. EV Chargers are in the design and procurement phase.

LRC EV Chargers

Level 2 and Level 3 electric vehicle chargers will be installed in the LRC parking lot, pending grant approval. 

Contact: 780-980-7107  /  engineering@leduc.ca
Timeline: Summer / Fall 2022, dependent on grant approvals
Funding: MCCAC Electric Vehicle Charging Program Grant Funding
Construction FAQs

Project Update:

Sept. 29, 2022 Preliminary wiring and Civil work are ongoing at the LRC, with the chargers expected to arrive in mid-December for install.
June 1, 2022 Scheduled - Design is complete and project is in procurement. 
May 6, 2022 Scheduled - in design and procurement phase. 
Feb. 17, 2022 Scheduled - Project currently in design phase. Additional information will follow prior to construction.