Simpson Park Multiway
With the Alberta Housing upgrade to the affordable housing units in Linsford, this made way for a 150m new multiway. This multiway will pass through Simpson Park, connecting residents to recreational areas in the community. As part of this project, the park will see the playground reinstalled.
Timeline: Spring - Fall 2020
Questions about this project?
Construction related questions:
Email: engineering@leduc.ca | Phone: 780-980-7107
Community Development questions:
Rachel Yeung, Manager, Community Development
Email: communitydevelopment@leduc.ca | Phone: 780-980-8441
Project updates
*Updates provided on a regular basis
Date | Status | Details |
September 21, 2020 | On-time | The last few fence posts have been placed. Fence anticipated to be completed this week. |
September 2, 2020 | On-time | Fence installation is nearly complete. One section requires the ground to dry out before installing. |
August 12, 2020 | On-time | Paving is complete. Fencing installation will begin within the next couple of weeks. |
July 29, 2020 | On-time | Contractor is completing subgrade preparations this week. Gravel and paving to follow. |
July 23, 2020 | On-time | Contractor on-site and subgrade preparation is ongoing.Gravel placement expected to begin late next week. |
July 15, 2020 | Scheduled | Contractor scheduled to be on site next week. |
July 9, 2020 | Scheduled | Due to heavy rain, access has been delayed until weather permits |
June 25, 2020 | Scheduled | No change. |
June 4, 2020 | Scheduled | Access to the site has been slightly delayed. The contractor is scheduled to start in early July. |
May 26, 2020 | Scheduled | Access to the site is scheduled for mid-June. Once access to the contractor is given work will commence. |