Lede Park Trail Connectors
Two sections of multiway will be built in Lede Park. The first is a 40m section connecting the LRC parking lot to the existing trail leading to the dog park. The second is a 245m section of trail connecting the existing trail to the north of the ball diamonds to the east to the existing trail north of the dog park.
Contact: | 780-980-7107 / engineering@leduc.ca |
Timeline: | 2022 - Details TBC |
Funding: | City of Leduc |
Construction FAQs |
Project Update:
Oct. 19, 2022 | Project has been completed. |
Sept. 21, 2022 | Landscaping remains adjacent to the new trail. |
Aug. 31, 2022 | General clean up and landscaping of the new trail have started. |
Aug. 18, 2022 | The trail was paved on August 12 and is nearing completion. General clean up of the area and landscaping still remain. |
Aug. 3, 2022 | Ongoing - Excavation of the new trail has begun. The gravel base is scheduled to be placed in the first week of August then followed by paving. The construction zone has been taped off with caution tape, please be cautious around the working zone. |
July 20, 2022 | Project begins - The portion of the trail that is north of baseball diamond #7 is scheduled to start constuction this week. |
June 1, 2022 | Scheduled - Project has been awarded. Construction expected to begin in July. |
Feb. 17, 2022 | Scheduled - Project currently in the design and procurement phase. Additional information will follow prior to construction. |
Feedback