Windrose Multiway

Update: Preparation for the trail will begin in beginning of 2020; construction anticipated to start in late spring.

Funding support: Provincial grant (MSI)

A key connection of Leduc’s multiway, this extension will join directly off of Black Gold Drive and run south along the Leduc Golf Course.  Thanks to the recent lease agreement between the City of Leduc and the Leduc Golf Course, the multiway has been aligned on most of the golf course lands. This alignment is an important part of connecting residents to a number of recreational and natural areas in our community. Fencing will be installed along the full length of the trail to create separation between trail users and the golf course. Specific areas will have the added safety feature of a canopy fence to shield users from rogue golf balls.

View the trail alignment. 

Questions about this project?

Construction related questions:
Email: engineering@leduc.ca | Phone: 780-980-7107

Community Development questions:
Email: communitydevelopment@leduc.ca | Phone: 780-980-8441

Project updates

*Updates provided on a regular basis

Date Status Details
September 21, 2020 On-time Fence is on track to be completed toward the end of this week. Topsoil and sod instillation will follow. 
August 12, 2020 On-time Fence installation is ongoing. 
July 29, 2020 On-time Topsoil placement is complete. Contractor is working on fence installation. 
July 23, 2020 On-time Paving of trail and topsoil placement are complete. Fence installation is starting. 
July 15, 2020 On-time Paving of the trail is complete. Topsoil placement will begin and fence installation to start next week.
July 9, 2020 On-time Gravel placement is complete. Asphalt pavement is delayed due to weather and is scheduled for next week, weather permitting. Topsoil placement will follow, as well as fence installation. 
June 25, 2020 On-time Subgrade preparation is complete. Gravel is being placed this week.
June 15, 2020 On-time Mulch and topsoil removal has been completed. Contractor will be working on subgrade preparation. There has been slight delays due to ongoing precipitation. 
June 4, 2020 On-time Construction started the first week of June. Removal of mulch and topsoil is ongoing.
May 25, 2020  Scheduled Construction is anticipated to start in early June.