Capital Roads Program - 59 Ave

59th Avenue between 47th Street and 50th Street

  • Will undergo a surface overlay
  • A concrete sidewalk will be added to connect 50th Street to the existing sidewalk section at the east end of this road.

Project Updates

DATE STATUS DETAILS
July 30, 2021 On-time Work is substantially complete.
July 22, 2021 On-time Paving and line painting is complete. Landscaping is ongoing.
July 15, 2021 On-time Paving complete. Landscaping and line painting are ongoing. 
July 7, 2021 On-time Milling will begin this week with paving to follow next week. 
June 30, 2021 On-time Milling will start week of July 5 followed by paving. This will be night work. 
June 24, 2021 On-time Sidewalk is complete. Milling and paving scheduled to start the week of July 5. 
June 16, 2021 On-time Sidewalk pour is scheduled for the end of this week. Milling of 59 Avenue is scheduled for early July.
June 9, 2021 On-time Sidewalk has been prepped and gravelled and is ready for concrete. 
June 2, 2021 On-time Removals for sidewalk installation will begin next week (June 7).
May 27, 2021 Scheduled Catch basins on the west end of 59th Avenue will be relocated this week. 
May 13, 2021 Scheduled The scope of work has been awarded and the contractor is planning the work, which is anticipated to begin in June. More updates to come when contractor is ready to move into the area. 
April 12, 2021 Scheduled Project currently in the design and procurment phase and additonal information will follow prior to construction.