Capital Roads Program - Southfork Drive

Southfork Drive between Hwy 2A and Southfork Drive, including the Hwy 2A intersection

  • Will undergo a surface overlay
  • Minor spot repairs will be made to concrete curb and the asphalt monowalk.

View Project Sketch


Project Updates

DATE STATUS DETAILS
July 22, 2021 On-time Work is substantially complete.
July 15, 2021 On-time Milling complete. Paving anticipated to be complete early next week. 
July 7, 2021 On-time Milling and paving expected to begin late this week and carry into next week as night work. 
June 30, 2021 On-time Milling to start late week of July 5 or the following week. This will be night work. 
June 24, 2021 On-time Concrete repairs have started and are expected to be complete toward the end of next week. Milling and paving is scheduled to start the week of July 5. 
June 18, 2021 On-time Paving in area of Southwick Point has been advanced to Saturday, June 19, and garbage collection will resume as per normal by laneway collection on June 21st. Impacted residents were provided notice by the contractor.
June 9, 2021 On-time Concrete repairs have been delayed due to weather, and will be rescheduled for the week of June 14 or 21. 
June 2, 2021 On-time Concrete repair work will commence next week (June 7). 
May 13, 2021 Scheduled The scope of work has been awarded and the contractor is planning the work, which is anticipated to begin in June. More updates to come when contractor is ready to move into the area. 
April 12, 2021 Scheduled Project currently in the design and procurment phase and additonal information will follow prior to construction.