Capital Roads Program - 59 Ave
59th Avenue between 47th Street and 50th Street
- Will undergo a surface overlay
- A concrete sidewalk will be added to connect 50th Street to the existing sidewalk section at the east end of this road.
Project Updates
DATE | STATUS | DETAILS |
---|---|---|
July 30, 2021 | On-time | Work is substantially complete. |
July 22, 2021 | On-time | Paving and line painting is complete. Landscaping is ongoing. |
July 15, 2021 | On-time | Paving complete. Landscaping and line painting are ongoing. |
July 7, 2021 | On-time | Milling will begin this week with paving to follow next week. |
June 30, 2021 | On-time | Milling will start week of July 5 followed by paving. This will be night work. |
June 24, 2021 | On-time | Sidewalk is complete. Milling and paving scheduled to start the week of July 5. |
June 16, 2021 | On-time | Sidewalk pour is scheduled for the end of this week. Milling of 59 Avenue is scheduled for early July. |
June 9, 2021 | On-time | Sidewalk has been prepped and gravelled and is ready for concrete. |
June 2, 2021 | On-time | Removals for sidewalk installation will begin next week (June 7). |
May 27, 2021 | Scheduled | Catch basins on the west end of 59th Avenue will be relocated this week. |
May 13, 2021 | Scheduled | The scope of work has been awarded and the contractor is planning the work, which is anticipated to begin in June. More updates to come when contractor is ready to move into the area. |
April 12, 2021 | Scheduled | Project currently in the design and procurment phase and additonal information will follow prior to construction. |