Capital Roads Program - Coady Boulevard

Coady Boulevard between Mcleod Crescent to just North of Middleton Close

  • Will undergo a surface overlay
  • This work will be completed while Caledonia Park School is closed for the summer.

View Project Sketch


Project Updates

DATE STATUS DETAILS
August 26, 2021 Complete Work is substantially complete.
August 18, 2021 On-time Milling started August 18. Paving and line painting are anticipated to be complete by the end of the week. 
July 30, 2021 On-time Milling and paving scheduled for late August.
July 7, 2021 On-time Concrete removals and restoration expected to begin next week. 
May 13, 2021 Scheduled The scope of work has been awarded. Work will begin in the summer months when school is out. 
April 12, 2021 Scheduled Project currently in the design and procurment phase and additonal information will follow prior to construction.