Capital Roads Program - 47 Street
47th Street between 54th Avenue and 61st Avenue
- Will undergo a surface overlay
- Due to width of 47th Street at 59th Avenue, a change in line painting will create a westbound turning lane.
- A pull-out parking area will be created on 47th Street, adjacent to the commercial business area at 61st Avenue and 50th Street.
Project Updates
DATE | STATUS | DETAILS |
---|---|---|
July 30, 2021 | On-time | Work is substantially complete. Minor landscaping items remaining. |
July 22, 2021 | On-time | Paving and line painting is complete. Landscaping is ongoing. |
July 15, 2021 | On-time | Paving complete. Landscaping and line painting are ongoing. |
July 7, 2021 | On-time | Milling to begin this week with paving to follow next week. |
June 30, 2021 | On-time | Milling will start week of July 5 followed by paving. This will be night work. |
June 24, 2021 | On-time | Concrete repairs have started and should be complete toward the end of next week. Milling and paving scheduled to start the week of July 5. |
June 16, 2021 | On-time | Milling scheduled for early to mid-July, with overlay scheduled shortly after. |
June 9, 2021 | On-time | Some approaches have been prepped for concrete. Work is ongoing. |
June 2, 2021 | On-time | Some concrete removal and rehabilitation work will begin next week (June 7). |
May 13, 2021 | Scheduled | The scope of work has been awarded and the contractor is planning the work, which is anticipated to begin in June. More updates to come when contractor is ready to move into the area. |
April 12, 2021 | Scheduled | Project currently in the design and procurment phase and additonal information will follow prior to construction. |