Capital Roads Program - Sparrow Drive
Sparrow Drive North of 65th Avenue (the first 1.2km)
- Will undergo a surface overlay
- Minor spot repairs will be made to concrete curb and commercial crossings.
- This road is provisional in scope and will be the last road approved to proceed, pending remaining budget for the annual road program.
Project Updates
DATE | STATUS | DETAILS |
---|---|---|
Oct. 7, 2021 | On-time | Milling and paving are scheduled to occur the week of Oct. 12, weather permitting. |
Sept. 30, 2021 | On-time | Milling and paving are scheduled for mid-Oct. |
Sept. 17, 2021 | On-time | Concrete repairs are ongoing. |
Sept. 1, 2021 | Scheduled | Storm catch basin repairs anticipated to start mid-September, followed by concrete removals. |
May 31, 2021 | On-hold | This project has been placed on hold as the funding has been re-directed to cover the emergent reconstruction of a failed lane in Southfork. This scope was provisionally awarded to the contractor and will be re-evaluated closer to the end of the season to determine if any of this project scope can be accommodated within the remaining road construction budgets for the season. |
May 13, 2021 | Scheduled | The scope of work has been awarded and the contractor is planning the work, which is anticipated to begin in June. More updates to come when contractor is ready to move into the area. |
April 12, 2021 | Scheduled | Project currently in the design and procurment phase and additonal information will follow prior to construction. |